Venue 03 / 07 · Pump Track
Fynbos Flow Circuit
Africa's first UCI pump track.
Area
23,820 m²
Capacity
200-400 riders daily
Capital programme
R100-140M
Standard
UCI Pump Track World Championships ready
The concept
Africa's first UCI pump track.
A 500m looping UCI-compliant circuit in three interconnected sections - beginner, intermediate, advanced - with branching paths for skill progression. Modular asphalt segments reconfigure for qualifiers and World Championship rounds.
Inspired by: Velosolutions Lisbon · UCI Aigle · URBNSURF skate integration
Build & cost profile
What it takes to build.
Extracted from the independent six-node venue analysis (August 2026). Capital ranges are the published Project Motion figures; construction programme, capex intensity and pricing are independent estimates benchmarked internationally and adjusted for South African conditions.
R100M-R140M
Estimated construction cost
3-6 months for the track; longer for the full site package
Estimated construction time
~R5,000 / m²
Capex intensity (midpoint)
23,820 m²
Footprint
Key cost drivers
- →Asphalt surfacing and finish tolerances
- →Earthworks and site shaping
- →Drainage and roof-water control
- →Berms, rollers and jump lines
- →Spectator areas and lighting
Build type
Indoor asphalt circuit under a clear-span roof
Indicative entry pricing
Indicative ~R120 day pass; highest accessibility across all ages
Role in the campus
High-volume community and multi-use asset with UCI flagship potential.
Safety & emergency response
How this node is kept safe.
Extracted from the Project Motion Safety, Medical, Emergency Response & Risk Management framework (August 2026). Quantities are preliminary recommendations pending validation against the final architectural plan, occupancy modelling and applicable South African standards.
On-node medical provision
2 first-aid boxes · 1 AED · 1 mobile trauma kit
Emergency priority
RED or AMBER depending on injury severity
Principal risks
- →Falls
- →Collisions
- →Over-speed
- →Inexperienced riders
- →Pedestrian intrusion
Operating controls
- ✓Rider segregation and defined entry and exit
- ✓Capacity limits and session management
- ✓Marshalling and speed management
- ✓Surface inspection and wet-surface closure
- ✓Emergency lane kept clear
Required staff competencies
First aid · CPR / AED · Marshal training · Surface inspection · Crowd control
Key features
What's built in.
- →Beginner, intermediate, and championship sections in one loop
- →Modular segments reconfigurable for events
- →Fynbos-lined interior borders and glazed Table Mountain sightlines
- →Drone-friendly lighting for tutorials and live content
Sustainability
How it's built green.
- ●Asphalt with 40-50% recycled aggregate and tyre rubber
- ●Recycled-plastic rollers and berms (10-20 tons of ocean waste)
- ●Solar LED lighting, interior bio-swales for water control
- ●WWTW-linked irrigation for surrounding gardens