Site selection & feasibility

Melkbosstrand. Ground first.

Three parcels assessed on the West Coast corridor between the R27 and the Melkbosstrand Wastewater Treatment Works. One of them can carry the entire discipline set on day one. All figures in ZAR.

Pre-acquisition - LOI in progressSite 3 is a single willing private seller at letter-of-intent stage. No acquisition agreement is signed and no rezoning application has been lodged.
3
Parcels assessed
3-6 months
Fastest route to ground
24,100 m²
Olympic-grade campus footprint
5 km
Inside Koeberg PAZ - 4-hour standard

Location

The West Coast corridor.

Melkbosstrand sits 35 minutes north of Cape Town on the R27, with Table Mountain on the southern horizon and the municipal wastewater works next door - the two assets the campus is designed around.

Table Mountain sightlines

Every parcel holds a clear southern view of the mountain - an irreplaceable broadcast and marketing asset for a media-first venue.

Melkbosstrand WWTW

The adjacent treatment works supplies the recycled water that runs the surf lagoon, dust control and fynbos irrigation.

Koeberg PAZ · NNR

On planning-grade distances from the published coordinates, the candidate parcels fall inside the 5 km Precautionary Action Zone - approximately 3.9 km at Site 2 and 4.5 km at Site 3 - which carries a 4-hour full-evacuation standard rather than the 16-hour sector standard applying in the 5-16 km Urgent Protective Action Zone. Occupancy is therefore gated on a validated evacuation time estimate, licensed survey and National Nuclear Regulator pre-application consultation. No clearance is claimed.

Three parcels assessed

Speed versus alignment.

The municipal parcels carry the Film City policy alignment and the R27 frontage. The private parcel carries the calendar. Coordinates as recorded in the CIO Master Report.

Site 1

ERF 1694 - Municipal

Melkbosstrand · R27 corridor

Owner
City of Cape Town
Route
PPP / long-term lease
Timeline
18-36+ months
Land entry
R15M - R40M
Visibility
Excellent - R27 frontage
Infrastructure
Greenfield (unserviced), ±151 ha total, ±20 ha PM footprint
WWTW access
200-400 m + R27 crossing
Principal risk
ABHOA litigation history · municipal inertia
Site 2

R27-Adjacent Parcel

33°42'29.0"S 18°27'04.0"E

Owner
City of Cape Town (within ERF 1694)
Route
PPP / long-term lease
Timeline
18-36+ months
Land entry
R15M - R40M
Visibility
Outstanding - direct R27 frontage
Infrastructure
Greenfield (unserviced)
WWTW access
200-400 m + R27 HDD crossing (R400K-R800K)
Principal risk
NNR density constraints · SANRAL TIA required
Site 3Preferred

Private Smallholding - Duynefontein

33°42'27.0"S 18°27'49.2"E (−33.7075, 18.4637)

Owner
Single willing private seller
Route
Private sale (half-parcel)
Timeline
3-6 months
Land entry
R15M - R30M
Visibility
Low - 1.3-1.6 km inland of the R27
Infrastructure
Existing 3-phase power, structures, possible borehole
WWTW access
650-850 m - no R27 crossing
Principal risk
PIE Act managed exit for existing occupants

The recommendation

Site 3 is the seed.

The private smallholding in the Duynefontein belt can host the full set of disciplines within its allotted size. Expansion onto ERF 1694 is an option, not a dependency - Site 3 is the seed, ERF 1694 is the harvest.

Why it leads
  • Hosts the complete discipline set - surf, BMX, pump, skate, climb and aerial - within the allotted parcel size.
  • Fastest route to ground in Melkbosstrand: 3-6 months versus 18-36 months for the municipal parcels.
  • Single willing seller - no tender, no council resolution, no MFMA Section 14 process.
  • Existing three-phase electricity, usable structures and a possible borehole for immediate Phase 1 works.
  • 650-850 m from the WWTW with no R27 crossing, saving the R400K-R800K directional drill.
  • Most wind-sheltered position of the three - a direct operational benefit for the surf lagoon.
  • No HOA public-participation process, and the existing community creates an authentic transformation narrative.
Risk register
  • Site 3PIE Act managed exit for informal occupants and business tenants - a 6-24 month delay risk if handled poorly.
  • Site 3Full standalone EIA required; no prior Basic Assessment Report data to leverage.
  • Site 3Agricultural zoning - rezoning required without a CoCT co-applicant.
  • Site 3No R27 frontage; wayfinding needs R2M-R5M of access road and signage.
  • Site 3Possible asbestos in older structures - hazmat survey before any demolition.
  • Sites 1 & 2Atlantic Beach HOA litigation history and eight years of stalled municipal development.
  • Sites 1 & 218-36+ month PPP timeline, MFMA compliance and SANRAL approvals before access can be built.

Phase 1 entry cost · ZAR

What it takes to break ground.

Site 3 acquisition and Phase 1 enablement, low and high estimates. All amounts in South African Rand.

Cost category
Low
High
Notes
Land acquisition (half-parcel)
R15M
R30M
Seller's ask; counter-offer basis
Occupant relocation / PIE management
R500K
R2M
Depends on number and cooperation of occupants
Environmental desktop + Phase 1 EIA launch
R150K
R400K
Standalone process - no prior BAR data
Asbestos / hazmat survey + demolition
R200K
R800K
If asbestos confirmed in existing structures
Access road upgrade + wayfinding signage
R2M
R5M
Duynefontein road network to visitor volumes
WWTW pipeline (650-1,000 m)
R3M
R7M
No R27 HDD crossing required
Electricity upgrade (3-phase existing)
R1M
R3M
Existing connection usable immediately
Phase 1 site works & early programming
R3M
R8M
Refurbishment for youth academy launch
Professional fees (legal, planning, EAP)
R1M
R2.5M
Conveyancing + PIE attorney + practitioner
Total - Phase 1 entry
R26M
R59M
R23M-R44M at the R12M-R15M half-parcel acquisition price

Source: CIO Master Report, May 2026 · Forward-looking estimates

Water economics

The cheapest water in the industry.

Project Motion is engineered to run on recycled municipal water - a tertiary UV and multimedia filtration upgrade at the Melkbosstrand WWTW turns an operating expense into an arbitrage. The method is established at surf parks internationally and is intended to be the first at this scale in South Africa.

R2-R8
Per kilolitre - recycled
R35-R45
Per kilolitre - potable
R90M-R250M
Saved over a 40-year lifecycle
R400K-R800K
R27 directional drill - Sites 1 & 2 only

Proven internationally

Surf parks already run on recycled water.

Feeding a large surf or recreational lagoon from treated, reclaimed water is established practice, not an untested idea. Several of the world's leading surf parks already do it.

  • Wavegarden facilitySpain

  • Adventure Parc SnowdoniaWales

  • URBNSURF MelbourneAustralia

  • Surf Ranch, LemooreCalifornia, USA

The facilities below are public industry reference examples only. Project Motion has no agreement, partnership or relationship of any kind with any of them.

Safe for human use

Treated to a standard set for people to swim in.

  • A regulated category, not an experiment

    Tertiary-treated recycled water for recreational water bodies is a defined, permitted use. California's Title 22 recycled-water rules and the equivalent Australian guidelines both set standards for lake fill and landscape impoundments, and South African use would be licensed and monitored under Department of Water and Sanitation and City of Cape Town conditions.

  • Off-the-shelf treatment train

    Multimedia filtration, UV disinfection, residual dosing and continuous turbidity and microbiological monitoring are standard, proven equipment specified daily for public swimming water. Nothing in the proposed plant is unproven technology.

  • Full-contact water quality

    The lagoon is designed to meet full-contact recreational water standards - the same class of standard applied to public pools and swimming beaches - with automatic monitoring and shutdown thresholds set by the water engineer appointed at design stage.

  • What it means for a surfer

    By the time water reaches the lagoon it has been treated and disinfected to a standard set for people to swim, surf and be fully immersed in, and it is tested continuously while the venue is open.

Pre-acquisition - LOI in progressDesign intent only. No treatment plant is built, no water-use licence is issued and no engineer is appointed. Water quality, monitoring regime and shutdown thresholds will be set by the appointed engineer and confirmed by the regulator before any public use.

Sequence over selection

Four phases, one campus.

The parcels are not competing options. They are sequential moves - each one strengthening the negotiating position for the next.

Phase 1
Seed
Site 3 - Duynefontein

Immediate private acquisition. Youth programming launches in refurbished structures, establishing a proven operational track record within 12-18 months.

R23M - R44M
Phase 2
Flagship
ERF 1694 - PPP

Execution of the municipal PPP. Construction of the surf lagoon and media studios as the anchor of the CoCT Film City mandate.

R178M - R320M
Phase 3
Mothership
Full campus

Complete campus and R27 arrival statement. Site 3 becomes the backstage - academy, athlete accommodation, tech lab. First African Action Sports Championship.

Balance of R530M programme
Phase 4
Franchise
Johannesburg · Lagos · Nairobi · Accra

Export the model. Franchise fee plus annual royalty on gross revenue, with Cape Town as the quality standard and brand authority.

R50M - R100M per city

Implementation

The 90-day sprint.

Day 1-30

Execute Lightstone / Deeds search on Site 3; initiate forensic PIE Act due diligence on informal occupants.

Day 31-60

Issue non-binding Letter of Intent for the northern half of Site 3 at a target price of R12M-R13M.

Day 61-90

Finalise and submit the four-page Partnership Concept Note to the CoCT Film Office to anchor the ERF 1694 PPP proposal.

Site pack available under NDA.

Deeds data, environmental scoping, WWTW engineering notes and the full three-site comparison matrix.